HYPOTHESIS
The construction of the 'Great Pyramid'.
A mystery for centuries; how was it done? A Construction Hypothesis by Norman Lucey.
Base levelling and establishing
and maintaining centre point
It is generally
accepted that the perimeter was levelled using a water trough set out in the basalt pavement around the perimeter.
The building was carefully oriented to north using a shadow rod (gnoman) and squared with ropes, leaving the rock
outcrop raised up within the central area, rough levelled to take the stones. The three pyramids on the Giza plateau
are arranged to avoid overshadowing. Each corner was carefully marked with a large limestone corner stone, set
in a floor socket and establishing, for all time, the angles of the faces and anticipated apex approx. 200 courses
above. The critical part of the exercise was the permanent establishment of the centre point which would be transferred
up the building as it progressed. With sand-storms and over the years this point would need to be indelibly carved
in stonework on a central tower constructed in the most careful manner.
Establishing working platforms/terraces
and access to them
It appears from the survey evidence
available that from the beginning, three significant working platforms were proposed, located at heights approx.
an eighth, a quarter and half way up the pyramid; the retaining walls getting progressively thicker towards the
bottom, taking account of the mass of material they would retain. A central masonry core tower continued through
this structure, possibly battered externally or stepped to permanently record working heights and the central position,
as the building progressed. This is the reason all the internal chambers and galleries are offset from the centre.
Retaining walls
and rubble infill
As these masonry
retaining walls were constructed in a similar manner to the mastaba, ramps supported
from within the profile of the structure were progressed and the volume to the rear of these walls filled with
rubble and sand.
Locations of
terraces and sorting stonework
It is proposed
that the locations of these terraces can be established from the positions of the solid internal retaining walls
and the range of stonework thicknesses exhibited in the backing stones now visible on the outside, after the removal
of the limestone casing. Great care was taken to select stones in progressively reduced thickness as they were
taken from the adjacent quarry seams. Each course was progressively reduced in size, driven by the criteria that
only smaller stones should be placed on top of larger more stable ones and making them easier to raise and install
above the working platform. The tops of these stones were trimmed if necessary to receive the next course. These
progressions in the stone courses originally surveyed by Petrie, clearly identify the
primary terraces and the intermediate ones created as working platforms.
Terrace edges
maintain external lines and levels
In order to maintain
and control the batter or rake of all four sides, the edges of each significant terrace would be completed with
an edging of raked control stones positioned in relation to the fixed centre point. This could only be done on
a level platform within the retaining walls. Once these were set out, then further terraces could be created above
and intermediate working platforms around the perimeter at intermediate levels between them. This established greater
control over the setting out of the building and avoided the possibility of cumulative errors through progressive
construction. There is evidence that the building was also set out from the middle of each side as it actually
has eight faces not four. This was important to maintain that all faces coincided at the same apex and did not
create a ridge configuration at the top. The only satisfactory method of making certain the sides of the pyramid
remained flush from top to bottom was to install a central strip of thicker guide stones from top to bottom on
each side with access ways beneath to maintain a route around the terraces, prior to commencing the rest of the
work. The silhouette of the building also indicates the locations of these terraces.
Positions of
ramps for access both up and down
All large stones
would be slid into position using timber sledges and levers. The lack of timber and its import from Lebanon
meant that it was a valuable resource. Arrangements would be put in place to allow materials and workers to move
both up and down the structure systematically. Survey evidence has suggested the locations of ramps between the
significant terraces. They were built within the overall structure of the build to avoid abortive work and filled
in progressively as the building was finished downwards from the top. The positions of ramp support masonry can
be seen in the survey with loose fill to the raked ramp surface and to terraces above and below. This also provides
evidence of the ramp gradients used and their suitability for sledges pulled by teams of oxen.
Use of compacted
sand decks to move and position stones
Due to the lack of timber it was
essential that working platforms were created only from the work as it progressed. Stonework could only be slid
into position from the interior of the building and carefully positioned against the previous stone. To reduce
the amount of redundant material hauled up the building, all facing stones would be raked in the quarry and once
on the working terrace sawn in conjunction with its neighbour with copper saws, before being levered into position
at the perimeter from the working platform to the side and rear. Levers would move the stone back and forth until
it was in line with the course below. Mortars were used on the casing joints to seal them from the weather. It
would be natural for the facing stones to be fitted together on the deck where there was working room before locating
it on the precipice. Backing stones, carefully selected for thickness would then back up these facing stones and
be covered with sand to provide a new flush working top surface for sliding the next stones. These backing stones
are all that can be seen today and the sand has been consequently lost. As
stones have to be manoeuvred around the terrace corners, the walls of these terraces are set back at this point.
This can be seen in the exiting notch on the NE corner and at the top. Originally known by the arabs as the half-way
point on the ascent.
Issues with settlement
(Kings Chamber)
There were obviously
considerable problems with settlement of the fill when constructing the Kings Chamber. So much so that granite
slabs were piled up to several layers above to weigh down the walls and bring the chamber to a stable position.
Unfortunately this settlement was not consistent due to the rigidity of the central core stonework and this is
evident in the cracked exposed soffit slabs and Petrie’s survey of distortion in the wall slabs. The floor slabs
in both chambers were installed separately between the walls to take account of this settlement and provide suitable
tolerance.
Removal of sand
from chambers - shutters and sand chute
Egyptian engineering
relied on the use of sand to transport and position stonework, either horizontally or vertically (as used for the
obelisks and raking roof and entrance slabs). To achieve this, internal chambers would have been filled with sand
to allow the positioning of stonework above. All internal stonework had to be tight and filled with plaster to
prevent the ingress of sand from above as construction continued, particularly above the King’s Chamber. This sand
could be dangerous and bury workers alive. It had to be compacted and controlled, hence the use of shutters at
the chamber entrance to hold back the sand and allow it be removed in a controlled fashion. This is why the top
of the Grand Gallery has a vee shaped stone to feed this sand into the chute that would take it out of the building.
During construction there was always the possibility of sand entering these areas by accident or from storms. It
had to be controlled and removed in a controlled fashion. The well shaft may have been a method of doing this as
it is not vertical and would be more suitable as a chute rather than for lifting water.
Working platforms
and steps to fix capstone
The positioning
of the capstone or pyramidion directly over the centre point, carefully plumbed up from
its position below, stone by stone, was obviously an event and celebration. Access to this perilous position would
have been created using working platforms supported from the terraced stonework below and with stone steps cut
in between these platforms. The capstone would have been levered up, wedged, blocked and raised to it’s
correct height above the top and final working platform and after the celebrations, battered limestone casing stones
fitted below. Great care would have been necessary to avoid the loss of this valuable capstone over the edge and
space would have been necessary around it for dignitaries. It is suggested that all this is done using support
from the structure itself and not from dangerous secondary timber platforms. The top platform was probably made
larger for this purpose. Once the capstone was laid on finished raked limestone facing stones, the finishing of
the building would progress downwards as described by Herodotus.
Access
steps and ramps would be progressively filled in and lost. Access would no longer be possible to the top.
Infilling ramps
and facing terraces, toothing in and progressing down
To allow stonework
to be fitted to the terraces and working platforms as they were built out and the work progressed downwards, there
is evidence of vertical stones, left to support the casing to allow other later stones to be toothed in below.
Due to the tolerance in fitting this work to the already finished stonework above, progressively thinner stones
were used to allow them to be raised and levered up on blocks by hand and slipped into position into the tapered
space. Final finishing of the facing stones in completed areas was undertaken by scaling ladder from the terrace
below.
Final finishing
and facing stonework
Herodotus states in book two
of his "Histories" that "the pyramid itself was twenty years in the making" and that "the whole is of stone polished
and most exactly fitted". The limestone facing stones are relatively easy to work, especially when fresh and not
case hardened. Tourists to the top confirmed how easy it was to carve graffiti in these stones and evidence of
sand erosion at the base and to the capping of the adjacent pyramid is clear. Hence the reason later pyramids used
granite for the plinth stones.
A large amount has been written
about the angles and dimensions within the pyramid. My own suggestion is that the internal passageways have been
arranged at a gradient of 1 in 2 and the pyramid at a batter of 5 in 4; all set out using their simple tools of
'A frame' and plumb bob for levelling, sighted with a merkhet and bay. The outer wall of the internal mastaba arranged at the traditional
4 in 1.
Interested / critical ?
contact me and let me know at............
e-mail:
Copyright © 2009 Norman Lucey. All rights reserved.
Click to open and view print ready version
|